In a November, 2020 photo, the aircraft carrier john F. Kennedy (CVN 79) sits at Pier 3 in ~ Newport News Shipbuilding. (Matt Hildreth/Huntington Ingalls)
*
*
*
*
*
*

NEWPORT NEWS, Va. (Tribune News Service) — The cost of the Navy’s following three carriers is ~ above the rise, early in component for environment of equipment and electronics to manage the brand-new F-35 share Strike Fighters.

You are watching: Cost of a ford class aircraft carrier

The Navy’s recent 390-page budget year 2022 spending plan justification record calls for increased spending because that the carrier man F. Kennedy’s electromagnetic catapult and also arresting gear — equipment that ran thousands of millions the dollars over budget for the USS Gerald R Ford, the command ship because that the Navy’s brand-new class that carriers.

All in all, the cost of the Kennedy, now an ext than 80% complete at Newport News Shipbuilding, will rise by $531 million, or 4.7% native the calculation in critical year’s justification document, come $11.93 billion, the Navy currently says.


The price of the third carrier in the Ford class, the Enterprise, will rise $84 million, to $12.41 billion, while the 4th carrier in the class, the Doris Miller, will watch a $33 million increase to $12.48 billion. Both ships are under building at Newport News.

The cost of Kennedy’s straightforward construction — the hull, structures and mechanical systems, is set to climb by $368 million.

The Navy said this will cover the expense of occupational to accommodate the F-35 fighters that room succeeding the Navy’s current FA-18 SuperHornets, as well as installing and integrating several of the equipment it is furnishing the ship now that it has moved come single-phase delivery.

The Navy had actually originally planned to accept delivery of Kennedy in two steps, usually to stretch out payments for the ship. The idea to be to avoid having actually both the Kennedy and USS Nimitz, the carrier it is replacing, in the fleet at the very same time. That would have actually stretched marine personnel and budgets more than Congress, earlier in 2016, wanted. The Navy chose to go back to a single-step shipment last November, together that issue eased.

Other F-35 related price increases because that the Kennedy incorporate $47 million for electronic devices systems.

In addition, the navy is adding $39 million because that a federal government test team and engineering support, now that the Kennedy is set for single phase delivery.


The cost of the Kennedy’s electromagnetic catapult, which is supplied to the shipyard by the Navy, is increasing by an additional $38 million, or 6.3%, native the year back estimate come $639 million, while its arresting gear price is up $11 million, or 4.7% to $243 million.

When the Navy very first included these system for Ford class carriers, it estimated the cost of the catapult at $318 million and also the arresting gear at $75 million. By the time the Ford itself to be commissioned, those prices had increased to $670 million for the catapult and also $148 million because that the arresting gear.

The costs of these two equipment for the following two Ford class carriers room steadying, however. The catapult is projected to price $608 million because that the Enterprise and also $593 million because that the Doris Miller.

Most of the climb in the cost of the Enterprise comes from work pertained to the F-35, including storage infrastructure for these planes and also some in addition to $29 million more for electronics systems to cover the enhancement of the new Joint Precision plane Landing System, the digital Consolidated Automated assistance System, adjustments to the carrier’s ready room and facilities for handling and storing lithium ion batteries.


The increased cost for the Doris müller comes mostly from the $22 million cost of including the share Precision plane Landing System, all set room modifications and lithium batter facilities, and $10 million from the the addition of MK-38 mod 3 machine Gun System and a logistics mechanism to support F-35s.

The budget file shows a $299 million, 4% decline in the cost of the two-boat a year Virginia course submarine program, wherein Newport News have assumed a larger share the the work. Congress last year returned production of Virginia course submarines come a two-a-year pace, rejecting a Trump administration slowdown.

See more: Chemicals In Wine That Cause Headaches ? Wine Headache: Causes, Treatment, Prevention Tips

The price of the an initial Columbia class ballistic missile submarines, on i m sorry Newport News Shipbuilding is structure the bow section, stern and sail, increased by $637 million, or 4.4%. Many of this increase comes to cover as whole planning and also design prices for the new boats.